Exhibit No. | Description |
---|---|
MH-1 | Manitoba Hydro letter to PUB dated November 29, 2016 re Timing of Electric GRA |
MH-2 | Manitoba Hydro letter to PUB dated March 24, 2017 re Intentions in respect of 2017 Rate Application(s) |
MH-3 | Manitoba Hydro letter to PUB dated April 12, 2017 re Minimum Filing Requirements & Scope of the Upcoming General Rate Application |
MH-4 | Manitoba Hydro letter dated May 5, 2017 re General Rate Application |
MH-5 | Manitoba Hydro 2017/18 & 2018/19 General Rate Application |
MH-6 | Manitoba Hydro letter dated May 12, 2017 re General Rate Application |
MH-7 | Manitoba Hydro cover letter dated May 26, 2017 re General Rate Application and MFRs |
MH-8 | Manitoba Hydro to PUB letter dated June 2, 2017 re August 1, 2017 Interim Rates |
MH-9 | Manitoba Hydro's Written Submission on Interim Rates dated June 20, 2017 |
MH-10 | Manitoba Hydro cover letter dated June 21, 2017 re General Rate Application and MFRs |
MH-11 | Manitoba Hydro cover letter dated June 23, 2017 re General Rate Application and MFRs |
MH-12 | Manitoba Hydro cover letter dated June 30, 2017 re General Rate Application and MFRs |
MH-13 | Manitoba Hydro letter dated July 11, 2017 re Updated Financial Forecast |
MH-14 | Manitoba Hydro CSI Process Motion - dated July 11, 2017 |
MH-14-1 | CSI Process Submission Schematic |
MH-15 | Manitoba Hydro Interim Rates August 1, 2017 Reply Submission - July 19, 2017 |
MH-16 | Presentation by Manitoba Hydro - Business Operations, Capital and Asset Management Technical Conference - July 20, 2017 |
MH-17 | Transcript of Proceedings - Business Operations, Capital and Asset Management Technical Conference - July 20, 2017 |
MH-18 | Response to the Coalition's letter re Cost of Service (COS) Model |
MH-19 | Manitoba Hydro Response letter to Intervener Budget Submission - July 21, 2017 |
COS Model acess - email dated July 26, 2017 | |
MH-21 | Manitoba Hydro Comments on Business Council of Manitoba's Budget Submission - July 28, 2017 |
MH-22 | Manitoba Hydro - Rate Schedules further to Order 80/17 - August 1, 2017 |
MH-23 | Proof of Revenues based on 2017 Electric Load Forecast - August 2, 2017 |
MH-24 | Manitoba Hydro to PUB re City of Winnipeg's Proposed Intervention dated August 2, 2017 |
MH-25 | Manitoba Hydro to PUB re Information Requests - August 2, 2017 |
MH-26 | Revised Rate Schedules to be Effective August 1, 2017 - Area & Roadway Lighting (Outdoor Lighting) Light Emitting Diode (LED) Rates - Letter dated August 24, 2017 |
MH-27 | Letter from KA Shepherd of Manitoba Hydro re First Round Information Requests - September 5, 2017 |
MH-28 | Manitoba Hydro - CSI Motion - September 7, 2017 |
MH-29 | Manitoba Hydro to PUB re Remaining Minimum Filing Requirements - September 7, 2017 |
MH-30 | Manitoba Hydro re Appendix 9.14 Report on Rate Design for the Residential Class - September 14, 2017 |
MH-31 | Manitoba Hydro to PUB re Independent Expert Consultants Status and Scope - September 18, 2017 |
MH-32 | Manitoba Hydro - CSI Motion - Round 1 Information Requests - September 21, 2017 |
MH-33 | Manitoba Hydro to PUB re Revised Information Requests - September 21, 2017 |
MH-34 | Manitoba Hydro to PUB re Independent Expert Consultants Scope of Work - October 2, 2017 |
MH-35 | Manitoba Hydro CSI Motion - Manitoba Hydro Reply to Intervenor Submissions - October 6, 2017 |
MH-36 | Manitoba Hydro to PUB re Round II Information Requests - October 16, 2017 |
MH-37 | Manitoba Hydro to PUB re Revised Round 1 Information Request - October 24, 2017 |
MH-38 | Manitoba Hydro Request to Review and Vary Order 112/17 - October 30, 2017 |
MH-39 | Manitoba Hydro to AMC Information Requests (1-8) |
MH-40 | Manitoba Hydro to Coalition (Compton/Simpson) Information Requests |
MH-41 | Manitoba Hydro to Coalition (ECS) Information Requests |
MH-42 | Manitoba Hydro to Coalition (METSCO) Information Requests |
MH-43 | Manitoba Hydro to Coalition (Simpson) Information Requests |
MH-44 | Manitoba Hydro to Coalition (MPA) Information Requests |
MH-45 | Manitoba Hydro to Green Action Centre (GAC) Information Requests |
MH-46 | Manitoba Hydro to GSS/GSM- KAP Information Requests |
MH-47 | Manitoba Hydro to MIPUG (Bowman) Information Requests (1-24) |
MH-48 | Manitoba Hydro to MIPUG (Osler/Forrest) Information Requests |
MH-49 | Manitoba Hydro to PUB revised MFRs |
MH-50 | Manitoba Hydro to City of Winnipeg (COW) Information Requests |
MH-51 | Manitoba Hydro - CSI Motion - Round 2 Information Request - November 21, 2017 |
MH-52 | Manitoba Hydro Rebuttal Evidence - November 22, 2017 |
MH-53 | Manitoba Hydro to PUB re BCM Budget Variance - November 24, 2017 |
MH-54 | Manitoba Hydro to PUB - IRs of IEC - November 24, 2017 |
MH-55 | Manitoba Hydro to Dr. Yatchew - Information Requests |
MH-56 | Manitoba Hydro to Daymark (Export) - Inforamtion Requests |
MH-57 | Manitoba Hydo to Daymark (Load Forecast) - Information Requests |
MH-58 | Manitoba Hydro letter to PUB re Response to Order 120-17 - November 28, 2017 |
MH-59 | Curriculum Vitae of Manitoba Hydro Policy Panel |
MH-60 | Curriculum Vitae of Manitoba Hydro Revenue Requirement Panel |
MH-61 | Manitoba Hydro letter to PUB re MH Electric Board - December 1, 2017 |
MH-62 | Quarerly Report Cover Letter - November 16-17, 2017 |
MH-63 | Opening Statement |
MH-64 | Opening Presentation by Kelvin Shephard and Jamie McCallum - December 4, 2017 |
MH-65 | Top 10 Information Requets |
MH-66 | Manitoba Hydro letter to PUB re Response to Letter of November 30, 2017 - December 4, 2017 |
MH-67 | Manitoba Chambers of Commerce - Our Plan to Restore Manitoba Hydro and Protect Manitobans |
MH-68 | Revenue Requirements Presentation - December 6, 2017 |
MH-68-1 | Page 29-I of Revenue Requirements Presentation |
MH-69 | Speaking notes from Public Information Session October 18, 2016 |
MH-70 | PUB to MH Information Request Round 1 56-a-c revised with Attachments |
MH-71 | Manitoba Hydro Undertaking 3 - 2018 DBRS Canadian Provincial Government Outlook Report |
MH-72 | Manitoba Hydro Undertaking 1 - IFF models to MH Electric Board |
MH-73 | Manitoba Hydro Undertaking 2 - IFF Models |
MH-74 | Manitoba Hydro Undertaking from Transcript Page 507 - Performance Tragets re: Coalition-MH I-144 |
MH-75 | Manitoba Hydro Board Counsel Question 1 - Cost of Heating with Carbon Levy |
MH-76 | Manitoba Hydro Board Counsel Question 3 - DSM Costs |
MH-77 | Curriculum Vitae of Manitoba Hydro of COSS Rate Design and Bill Affordability Panel |
MH-78 | Manitoba Hydro Undertaking 5 - Operating and Adminstrative Costs |
MH-79 | Manitoba Hydro Undertaking 6 - Updated PUB MFR 55 and MIPUG-MH I-14b |
MH-80 | Manitoba Hydro Undertaking 9 - Updated Chart from MIPUG 32-2 page 83 |
MH-81 | Manitoba Hydro Undertaking 10 - 12 Year WATM |
MH-82 | Manitoba Hydro Undertaking 11 - 20 Year WATM |
MH-83 | Manitoba Hydro to PUB - Rebuttal Evidence on Daymark - December 15, 2017 |
MH-84 | Manitoba Hydro Undertaking 7 -MH-68 Slide 72 updated |
MH-85 | Manitoba Hydro Undertaking 8 - chart starting at 1990 on MH-68 Slide 72 |
MH-86 | Manitoba Hydro Undertaking 12 - IFF without payments to Government |
MH-87 | Manitoba Hydro Undertaking 4 - Provincial Equity Injection |
MH-88 | Manitoba Hydro Cost of Service, Rate Design and Bill Affordability Panel Presentation |
MH-89 | Manitoba Hydro Undertaking 28 -Appendix 3.8 Updated with 2.26 % interim, effective August 1, 2016 |
MH-90 | Manitoba Hydro Undertaking 15 - Avoided infrastructure costs for Generation Marginal Value Calculations |
MH-91 | Manitoba Hydro Undertaking 19 - Change in Methodology and why the chage was made |
MH-92 | Manitoba Hydro to MGF - Information Requets |
MH-93 | Manitoba Hydro Follow-up to Undertakings 7 & 8 -MH-68 Slide 72 |
MH-94 | Manitoba Hydro Undertaking 24 - 2014 Residential Energy Survey |
MH-95 | Manitoba Hydro Undertaking 16 - Countries instituted bill affordability programs |
MH-96 | Manitoba Hydro Undertaking 20 - explanation why marginal values changed under new methodology |
MH-97 | Manitoba Hydro Undertaking 29 - 10,000 payments to accounts of First Nation customers receiving socail assistance |
MH-98 | Manitoba Hydro Undertakings 21-23 - Figure 7 of AMC-MH II-23, LICO-125 and 6 percent threshold |
MH-99 | Manitoba Hydro Undertaking 17 - Meter Maintenance Subfunctionalizing distribution of poles, wires and substations |
MH-100 | Manitoba Hydro Undertaking 27 - 20 year levelized marginal values |
MH-101 | Manitoba Hydro Undertaking from Transcript page 2396 - Updated Figure 8.14 (Tab 8) |
MH-102 | Manitoba Hydro Undertaking 18 - Performance Optimization Programs |
MH-103 | Manitoba Hydro Undertaking 14 - Rate Increases across Canada |
MH-104 | Manitoba Hydro Projected Annual Residential Electric Bills |
MH-105 | Manitoba Hydro Undertaking 37 - Updated Slide 15 of MH-88 |
MH-106 | Manitoba Hydro Letter to Public Utilties Board re Review and Variation in Daymark Energy Advisors Saskpower Report - January 5, 2018 |
MH-107 | Manitoba Hydro Letter to Public Utilties Board re withdrawl of R&V in Daymark Energy Advisors Saskpower Report - January 9, 2018 |
MH-108 | Manitoba Hydro Undertaking 32 - Elecrically Heated single detached homes on reserve and off reserve |
MH-109 | Maniotba Hydro Undertaking 38 - Geothermal Program |
MH-110 | Manitoba Hydro Undertaking 34 - 2016/17 year for Load Displacement Program |
MH-111 | Manitoba Hydro to MGF Information Requests - Responses from KCB |
MH-112 | Manitoba Hydro Undertaking 35 - DSM Expenditures |
MH-113 | Manitoba Hydro Undertaking 25 - MKO First Nation Revenue |
MH-114 | Manitoba Hydro Undertaking 26 - MKO Revenue at 7.9% |
MH-115 | Manitoba Hydro Undertaking 30 & 31 - Generation Marginal Value |
MH-116-1 | Manitoba Hydro Book of Documents 1 for Cross Examination of Morrison Park Advisors |
MH-116-2 | Manitoba Hydro Book of Documents 2 - Cross Examination of MIPUG Patrick Bowman, Cam Osler and Gerry Forest |
MH-116-3 | Manitoba Hydro Book of Documents 3 - Cross Examination of GSS-GSM London Economic International |
MH-116-4 | Manitoba Hydro Book of Documents 4 - Cross Examination of MGF |
MH-117 | Manitoba Hydro Rebuttal of MGF Evidence |
MH-118 | Manitoba Hydro - Major Capital Projects Panel CV's |
MH-118-1 | CV of Lorne Midford |
MH-118-2 | CV of Glenn Penner |
MH-118-3 | CV of Dave Bowen |
MH-118-4 | CV of Jeff Strongman |
MH-118-5 | CV of Alastair Fogg |
MH-119 | Manitoba Hydro to PUB re Revised MGF Redacted Report - January 19 2018 |
MH-120 | Manitoba Hydro Major Capital Panel Presentation - January 22 2018 |
MH-121 CSI | Manitoab Hydro Major Capital Panel CSI Presentation |
MH-122 | Manitoba Hydro Undertaking 33 - Variation from order 116/08 |
MH-123 | Manitoba Hydro Underatking 36 - Projection for Load Displacement |
MH-124 | Manitoba Hydro Undertaking from Transcript Page 3088 - Status Update to Page 220 of Order 5/12 |
MH-125 | Manitoba Hydro Undertaking 54 - Presentation of Dr. Swatek - Need of Bipole III |
MH-126 | Manitoba Hydro Undertaking 58 - Estimated costs of Bipole III |
MH-127 | Manitoba Hydro Undertaking 59 - Road costs attributed to Conawapa |
MH-128 | Terms of Reference for NFAT |
MH-129 | Manitoba Hydro letter to all parties re Legal Argument - January 29, 2018 |
MH-130 | Manitoba Hydro letter to PUB re CSI in MGF Rebuttal |
MH-131 | Manitoba Hydro Undertaking 55 - Manitoba Hydro Control Schedule |
MH-132 | Manitoba Hydro Undertaking from Transcript Page 2640 - Solar and other Non-Utility Generation system credits |
MH-133 | Manitoba Hydro Undertaking 56 - payments to KPMG |
MH-134 | Manitoba Hydro Undertaking 63 - % of First Nations and Indigenous person working on Keeyask |
MH-135 | Manitoba Hydro Rebuttal Presentation |
MH-135-1 | Morrison Park Advisors Analysis Chart |
MH-136 | Manitoba Hydro Oral Argument - February 5, 2018 |
MH-137 | Manitoba Hydro Written Argument |
MH-138 | Manitoba Hydro Undertaking 60 - Most recent Monthly Report |
MH-139 | Manitoba Hydro Undertaking 53 - Distance between Bipole I and Bipole II |
MH-140 | Manitoba Hydro Additional MH16 Update with Interim Scenarios |
MH-140-1 | Manitoba Hydro Additional MH16 Update with Interim Scenarios - Revised with Redactions |
MH-141 | Manitoba Hydro Undertaking 57 - Keeyask Termination Costs |
MH-142 | Manitoba Hydro Reply - February 14, 2018 |