Exhibit No. | Description |
---|---|
LCA-1 | La Capra/Manitoba Hydro Round 1 Information Requests |
LCA-2 | La Capra/Manitoba Hydro Round 2 Information Requests |
LCA-3 | La Capra Associates Main Report |
LCA-3-1 | La Capra Associates Main Report – March 2014 Redacted |
LCA-3-2 | Supplemental Expert Analysis Report |
LCA-3-3 | LCA Supplemental Report A – Updated Figures |
LCA-3-4 | LCA Supplemental Report B - Observations |
LCA-4 | Technical Appendix 1 - Resource Planning |
LCA-4-1 | Technical Appendix 1 - Resource Planning - March 2014 Redacted |
LCA-5 | Technical Appendix 2 - Generation Alternatives |
LCA-5-1 | Technical Appendix 2 - Generation Alternatives - March 2014 Redacted |
LCA-6 | Technical Appendix 3 - Alternative Resource Plans |
LCA-6-1 | Technical Appendix 3B - Alternative Resource Plans |
LCA-7 | Technical Appendix 4 - Environmental Issues and Policy |
LCA-7-1 | Technical Appendix 4 - Environmental Issues and Policy - March 2014 Redacted |
LCA-8 | Technical Appendix 5 - Hydrological Risk |
LCA-9 | Technical Appendix 6 - Export Markets |
LCA-9-1 | Technical Appendix 6 - Export Markets - March 2014 Redacted |
LCA-10 | Technical Appendix 7 - Export Contracts |
LCA-10-1 | Technical Appendix 7A - Export Contracts - March 2014 Redacted |
LCA-10-2 | Technical Appendix 7B - Export Contracts |
LCA-11 | Technical Appendix 8 - Transmission |
LCA-12 | Technical Appendix 9 - Economic Analysis |
LCA-12-1 | Technical Appendix 9B - Economic Analysis |
LCA-12-2 | Addendum to Technical Appendices 9A and 9B |
LCA-13 | Technical Appendix 10 - Financial Analysis |
LCA-13-1 | Technical Appendix 10B – Financial Analysis |
LCA-14 | Incremental CPV Bar Charts, Break Even Years |
LCA-15 | Total Capital Expenditures |
LCA-16 | Worksheet - Cash Flows and Cumulative Incremental CF for P 4, 5, 6, and 14 |
LCA-17 | Summary of Expected Economic Value |
LCA-18 | S-Curves of Selected Plans, 78 Years, Sensitivity |
LCA-19 | S-Curves of Plan 14 and Plan 5 |
LCA-20 | S-Curves of Selected Plans, 10% Higher Capital Costs for Hydro |
LCA-21 | S-Curves of Selected Plans, All Higher Capital Costs for Hydro |
LCA-22 | Resource Plan Economic Benefits to the Province of Manitoba |
LCA-23 | S-Curves of Selected Plan, Province of Manitoba Perspective |
LCA-24 | Probability Distributions |
LCA-25 | Probability Distributions - LCA Sensitivity Discount Rates |
LCA-26 | Probability Distributions - 10% Higher Capital Costs for Hydros |
LCA-27 | Probability Distributions - Higher Capital Costs for Hydros all Scenarios |
LCA-28 | Probability Distributions - Variation in High & Low Capital for Thermal & Wind |
LCA-29 | Probability Distributions - No Variation in High & Low Capital for Thermal & Wind |
LCA-30 | Probability Distributions, Province of Manitoba Perspective |
LCA-31 | Figure 6-03 - Exports Before/After Keeyask |
LCA-32 | Figures 6-09, 6-11, 6-13, 6-14 - Energy Mix Charts |
LCA-33 | Figures 6-15, 6-18 - MHEB Historical LMPs with Charts |
LCA-34 | Figure 6-19 - MISO MP History Charts |
LCA-35 | Figure 6-40 - MISO Fuel Mix |
LCA-36 | Figures 4-4, 4-5 NPV Impact of Climate Change Cases |
LCA-37 | Figure 8-30 - Transmission Cost Exposure of Development Plan that Include the Conawapa GS |
LCA-38 | La Capra Associates - Dynamic Rates Model - Ref Case |
LCA-39 | La Capra Associates - POE Quilt Model (App. 11.3) |
LCA-40 | La Capra Associates - Rate Quilt Model (App. 11.4) |
LCA-41 | La Capra Associates - Tech Appendix 10 - Figures |
LCA-42 | La Capra Associates - Revenue LCOE Quilt Model (App. 11.4) |
LCA-43 | TA1 Resource Planning Figures |
LCA-44 | LCA Exhibits 14-43 Filed Electronically (LCA Worksheets) |
LCA-45 | LCA Direct Testimony Presentation - Part I |
LCA_46 | Scope of Work for La Capra Associates (LCA) |
LCA-47 | LCA Direct Testimony Presentation - Part II |
LCA-48 | LCA Errata Sheet |
LCA-49 | Und #100 - Mr. Hahn Hydro Electric Experience |
LCA-50 | Und #101 - Updated Capital Costs |
LCA-51 | Und #102 - See Und #101 Exhibit LCA-50 |
LCA-52 | Und #103 - Cross Over Point for Wind/Gas Option |
LCA-53 | Und #104 - Clarification of Information Sources - Slide 16 of LCA-48 |
LCA-54 | Und #105 - Analysis of Plant 5, 6 and 2 |
LCA-55 | Und #106 - NPV for Figures 9-94 and 9-95 of LCA Report |
LCA-56 | Und #107 - Revised "S" Curve |
LCA-57 | Und #108 - Revised PDP Component Values |
LCA-57-1 | Supplemental Response to Und #108 – Revised PDP Component Values |
LCA-58 | Und #109 - GNTL Costs |
LCA-59 | Und #110 - Rate Change Impacts |
LCA-60 | Und #111 - Net Debt impacts to LCA Model |
LCA-61 | Und #112 - Fuel and Power Purchase Model Impacts |
LCA-62 | Und #113 - Modelling of 34 year sequence |
LCA-62-1 | LCA Working Paper 113a Dynamic Rates Model RED Case 1912 Drought |
LCA-62-2 | LCA Working Paper Dynamic Model Case 2007 Drought |
LCA-62-3 | LCA Working Paper 113c Dynamic Rates Model REF Case 1916 Drought |
LCA-62-4 | LCA Working Paper 113d Dynamic Rates Model REF Case 1918 Drought |
LCA-63 | Und #114 - No New Generation Plan Financial Statements |
LCA-63-1 | LCA Working Paper 114a Dynamic Rates Model REF Case Supp Alternative POE |
LCA-63-2 | LCA Working Paper 114b Tech Appendix 10b - Financial Analysis Supp Workpaper |
LCA-64 | Und #115 - Surplus Energy from CCGT Plan vs PDP |